New Delhi: Power Grid Corporation of India Limited (POWERGRID) has approved an estimated investment of Rs 220.09 crore to upgrade a key high-voltage transmission line in southern India.
The company's Committee of Directors on Investment on Projects cleared the proposal at its meeting on 16 November 2026. POWERGRID disclosed the approval in a regulatory filing under Regulation 30 of the SEBI Listing Obligations and Disclosure Requirements Regulations, 2015.
Project to Upgrade 400 kV Transmission Corridor
The project involves reconductoring the Gooty-Tumkur (Pavagada) 400 kV double-circuit transmission line using High-Temperature Low-Sag (HTLS) conductors.
The key details are:
Estimated investment: Rs 220.09 crore
Approving authority: Committee of Directors on Investment on Projects
Approval date: 16 November 2026
Technology: High-Temperature Low-Sag conductor
Scheduled commissioning: 10 June 2028
Focus on Power Transmission Capacity
The Gooty-Tumkur transmission corridor connects Andhra Pradesh and Karnataka and supports power evacuation from the Pavagada solar hub.
The use of HTLS conductors is expected to increase the power-carrying capacity of the existing transmission line while retaining the existing tower infrastructure. This can help avoid the need for additional land acquisition and reduce right-of-way-related challenges associated with developing new transmission routes.
The upgrade is aimed at strengthening the transmission network and supporting the movement of electricity across the region.