New Delhi: The Ministry of Power has allowed renewable energy (RE) projects awarded through inter-state transmission system (ISTS)-connected tenders to connect to the state transmission network when the project and its procurer, such as a state electricity distribution company (DISCOM), are located in the same state.
The decision was communicated through a letter dated 10 November to the heads of NTPC, NHPC, SJVN and the Solar Energy Corporation of India (SECI). These organisations act as Renewable Energy Implementing Agencies (REIAs), inviting bids for renewable energy projects.
The ministry's decision follows a request from the National Solar Energy Federation of India (NSEFI), which sought permission for projects awarded under ISTS-connected tenders to use the State Transmission Utility (STU) or intra-state transmission system (InSTS) when both the project and procurer are located within the same state.
Decision Aims to Optimise Transmission Costs
The Ministry of Power said it had examined the proposal and agreed to it, citing the potential for transmission cost savings and benefits to procurers.
According to the ministry's letter, connecting renewable energy projects to the intra-state transmission network would generally help optimise transmission costs.
Under the existing ISTS-connected arrangement, a renewable energy project connects to the inter-state transmission network, through which the procurer receives power. The revised provision allows projects supplying buyers within their own state to connect directly to the state's transmission network instead.
The change is expected to provide greater flexibility in transmission planning and help reduce costs where intra-state connectivity is more suitable.
State Regulators to Approve Power Agreements
The ministry has clarified that intra-state power procurement is governed by the regulatory framework of the respective State Electricity Regulatory Commissions (SERCs).
Accordingly, where a renewable energy project and its procurer are located in the same state, the concerned SERC or Joint Electricity Regulatory Commission (JERC) may be approached for approval of the Power Purchase Agreement (PPA) or Power Sale Agreement (PSA) for the InSTS-connected procurement.
The provision brings regulatory approval within the framework applicable to intra-state power procurement, while allowing renewable energy projects awarded through ISTS tenders to use state-level transmission infrastructure under the specified conditions.